St. Thomas Street

Period: February 1998 - May 1998
Contract: St. Thomas St. (Belize City)
No. 383/97-80
Country: Belize
Employer: Government of Belize
Employer's Address: Ministry of Works
Power Lane,
Belmopan
Nature of Works:

A.Rehabilitate St. Thomas Street to a 4 lane
bitumen surface street with a median.
Length – 820m.
Surface Pave 12,000 m2.
B. Construct Median

Role: Sole Contractor
Total Value of Contract: Awarded - Bz. $873,080.00
US$436,540.00
Contract Awarded: February 10, 1998
Period: 6 Months
Completion Date: April 25, 1998 (1st seal)
Funding Agency:

Description:

The contract was completed 4 months ahead of contract completion date and under the contract value.