Burrell Boom Bridge

Period: November 2000 - February 2004
Contract: Burrell Boom Road Western Highway to Northern Highway 19.2 km No. 78/2000-01
Country: Belize
Employer: Government of Belize
Employer's Address: Ministry of Works, Power Lane, Belmopan
Nature of Works:

Rehabilitate 19.2 kms. Construction 1 – 100 meter long bridge

Role: Sole Contractor
Total Value of Contract: BZ $20,500,000 US $10,250,000
Contract Awarded: November 2000
Period:
Completion Date: February, 2003
Funding Agency:

DSC00137Boom-Bridge2

Description:

Salient Points of the Contract:

  • Over 400,000 M3 of material used.
  • Over 350,000 M2 paved.
  • 1 – 100m long 9.22m wide bridge constructed.
  • 60-steel casing piles driven for piers.
  • 30-concrete piles driven for abutments.
  • Over 6,500m of outlet channel drains excavated.
  • 1,756 linear meters of pipes placed in culverts